Project Risk Lab
Interactive tools for forecasting projects, making decisions under uncertainty and valuing carbon and nature. They draw on the book I co-authored, on my current research and on my teaching.
Start here
-
Reference Classes
Choose a project type and enter an estimate to see how far completed projects of that type ended from their estimates.
Two views
-
The Portfolio Game
Fund proposals within a fixed budget, then reveal their final costs and see how the funded set compares with the estimates.
-
Nature in the Business Case
Enter the costs and benefits of a project and see how its net present value changes when nearby nature is counted.
Two views
More tools
-
The Value of a Tonne of Carbon
See how the published value of a tonne of carbon dioxide depends on the discount rate and at which value an appraisal changes sign.
-
Long-Lived Assets
See what a dollar received in 60 years counts for today and how likely a rare event is over the life of an asset.
-
Monte Carlo Simulator
List the risks of a project with their probabilities and impacts, run the simulation and see the range of total cost.
-
Calibration Quiz
Give a 90 percent range for each of ten quantities and see how many of the true values fall inside your ranges.
-
Value of Information
Describe an uncertain quantity and a decision threshold and see what a measurement is worth before you pay for it.
-
Risk Matrix Roulette
Play three short rounds with a risk matrix and see where it ranks risks differently from their expected losses.
-
Probability Words
Set the probability you read into words such as likely and see the lowest and highest answer each received in an experiment.
-
Few Trials, Zero Failures
Enter a number of trials and failures and see the estimated failure rate and its upper bound after few or no failures.
-
Noise and Selection
Set the noise in estimates and the share of proposals funded and see how far funded projects end above their estimates.
-
The Sorting Machine
Set the degree of sorting among home buyers and compare the price difference across all homes with the difference within parishes.
-
Parade of Trades
Roll a die each week for five trades working through 35 rooms and watch variation in weekly output delay the finish.
Reference Classes
What you will learn How completed projects of the same type ended against their estimates and what budget or schedule would have been enough for a chosen share of them.
Choose a project type, enter your estimate and set a certainty level. The chart and the figures under it show how the completed projects in that class ended, scaled to your estimate.
The share of the completed projects in the class for which the budget shown would have been enough.
Final cost at each percentile of the class
- Completed projects in the class
- Reported in the book
- Your estimate
- The level you chose
How it works
A reference class is a set of completed projects of the same type. The book describes a forecast that is based on such a class as taking the outside view. For each project the book divides the final outcome by the estimate made at the final investment decision. A ratio of 1.00 means that the project ended on its estimate, a ratio of 1.28 that it ended 28 percent above the estimate and a ratio of 0.90 that it ended 10 percent under it.
Appendix 2 of the book reports the number of projects, the mean, the standard deviation and five percentiles of this ratio for each class. The 80th percentile, for example, is the ratio that 80 percent of the projects in the class ended at or below. The tool multiplies your estimate by these ratios.
The reported percentiles are the 5th, 25th, 50th, 75th and 95th. For a level between two of them the tool reads the value from a smooth curve through the five reported points, which never falls as the percentile rises. A figure read between two reported percentiles is therefore an approximation, which the result marks with the word about. The curve is a monotone cubic interpolation, fitted to the logarithm of the ratio where all five values are positive. The chart stops at the 5th and the 95th percentile because the book reports nothing beyond them.
The certainty level is the share of the completed projects for which a budget or a schedule would have been enough. The book calls it the required certainty of the estimate. At 80 percent, four in five of the projects in the class ended at or below the figure and one in five ended above it. For benefits the level is read from the other end of the class, so that 80 percent of the projects delivered the benefit shown or more.
The tool opens on the example that the book gives, a hospital with a cost estimate of $800 million. At the median ratio for hospitals of 1.02 the budget becomes $816 million, which the book describes as a 50 percent chance of delivering the hospital within the budget. At the mean ratio of 1.25 it becomes $1 billion. The mean reflects the few projects that ended far above their estimates. The book notes that planning with the mean makes sense where a large portfolio of hospital projects is considered. The tool shows amounts as plain numbers in million, so that the figures can be read in any currency.
A reference class describes projects as a group and does not describe what is particular to one project. The book notes that a bottom-up estimate would generally be better at addressing the parts of a project that differ from its reference class. The Monte Carlo Simulator builds the range of total cost for one project from its own risks. A ratio exists only for a project that was approved and completed. Noise and Selection draws on my current research to show how the choice of which projects to approve can affect these ratios.
The cost classes as a table
The table reproduces Table A2.1 of the book without the standard deviation. The mean and the percentiles are ratios of final cost to the estimate made at the final investment decision, with costs adjusted for inflation. The tool also uses the corresponding figures for schedule in Table A2.2 and for benefits in Table A2.3.
| Project type | Projects | Mean | P5 | P25 | P50 | P75 | P95 |
|---|---|---|---|---|---|---|---|
| Aerospace | 97 | 1.56 | 0.96 | 1.13 | 1.38 | 1.86 | 2.58 |
| Airports | 33 | 1.50 | 1.00 | 1.12 | 1.33 | 1.69 | 2.51 |
| Battery Storage | 10 | 1.07 | 0.87 | 1.00 | 1.08 | 1.17 | 1.24 |
| Bridges | 79 | 1.58 | 0.83 | 0.94 | 1.07 | 1.42 | 2.78 |
| Buildings | 226 | 1.62 | 0.83 | 1.00 | 1.11 | 1.43 | 3.46 |
| Bus Rapid Transit | 40 | 1.12 | 0.79 | 0.95 | 1.05 | 1.25 | 1.72 |
| CCUS | 31 | 1.28 | 0.85 | 1.02 | 1.18 | 1.36 | 2.10 |
| Dams | 329 | 1.68 | 0.80 | 0.99 | 1.25 | 1.72 | 4.19 |
| Data Centers | 22 | 1.02 | 0.82 | 0.94 | 1.00 | 1.04 | 1.33 |
| Defense | 143 | 1.42 | 0.67 | 0.96 | 1.03 | 1.36 | 3.74 |
| E-hydrogen | 7 | 1.14 | 0.96 | 1.00 | 1.00 | 1.32 | 1.40 |
| Electrical Substations | 25 | 1.11 | 0.91 | 1.00 | 1.10 | 1.13 | 1.42 |
| Electrical Transmission Lines | 51 | 1.32 | 0.62 | 0.92 | 1.07 | 1.22 | 1.96 |
| Energy Infrastructure Decommissioning | 31 | 1.56 | 0.79 | 1.00 | 1.25 | 1.93 | 3.13 |
| EV OEM | 17 | 1.45 | 1.00 | 1.00 | 1.00 | 1.11 | 2.75 |
| Hospitals | 102 | 1.25 | 0.97 | 1.00 | 1.02 | 1.22 | 2.06 |
| IT | 5,403 | 1.73 | 0.35 | 0.82 | 1.00 | 1.24 | 3.35 |
| Mining | 547 | 1.34 | 0.86 | 1.00 | 1.08 | 1.42 | 2.49 |
| Nuclear Power | 210 | 2.25 | 1.01 | 1.17 | 1.65 | 2.83 | 5.18 |
| Nuclear Storage | 23 | 3.32 | 0.71 | 1.32 | 1.49 | 3.26 | 13.05 |
| Oil and Gas | 161 | 1.32 | 0.80 | 1.00 | 1.17 | 1.36 | 2.22 |
| Paper Mills | 21 | 1.02 | 0.89 | 1.00 | 1.00 | 1.06 | 1.14 |
| Pipelines | 463 | 1.16 | 0.70 | 0.90 | 1.10 | 1.20 | 1.70 |
| Ports | 26 | 1.06 | 0.74 | 0.99 | 1.00 | 1.02 | 1.28 |
| Prisons | 19 | 1.18 | 1.00 | 1.10 | 1.11 | 1.21 | 1.57 |
| Pumped Storage Hydropower | 43 | 1.56 | 0.87 | 1.00 | 1.22 | 1.48 | 4.16 |
| Rail Stations | 70 | 1.53 | 0.83 | 1.00 | 1.18 | 1.60 | 3.31 |
| Railways | 555 | 1.34 | 0.77 | 1.00 | 1.16 | 1.50 | 2.09 |
| Roadways | 1,263 | 1.29 | 0.73 | 1.00 | 1.13 | 1.32 | 1.95 |
| Solar Power | 50 | 1.02 | 0.76 | 0.98 | 1.00 | 1.09 | 1.30 |
| Stadia | 50 | 1.45 | 0.94 | 1.02 | 1.21 | 1.50 | 3.08 |
| Steel Mills | 19 | 1.28 | 1.09 | 1.13 | 1.18 | 1.27 | 1.54 |
| Thermal Power | 168 | 1.16 | 0.62 | 0.93 | 1.08 | 1.28 | 1.84 |
| Tunnels | 67 | 1.40 | 0.77 | 0.99 | 1.22 | 1.58 | 2.61 |
| Wastewater Treatment | 22 | 1.15 | 0.87 | 0.95 | 1.02 | 1.26 | 1.87 |
| Water | 318 | 1.14 | 0.72 | 0.94 | 1.07 | 1.26 | 1.76 |
| Wind Power | 94 | 1.16 | 0.83 | 0.99 | 1.01 | 1.18 | 1.79 |
Sources
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Appendix 2, Tables A2.1 to A2.3, and Chapter 7.
All Classes at a Glance
What you will learn How the spread of outcomes around the estimate differs from one type of project to another.
Each row shows one class as the range of ratios between the final outcome and the estimate. Select a row to open that class in the forecast with your own estimate.
Final cost divided by the estimate, for each project type
- 5th to 95th percentile
- Middle half of the projects
- Median
- Outcome equal to the estimate
How it works
Each row summarises one line of Tables A2.1 to A2.3 in Appendix 2 of the book. The thin line runs from the 5th to the 95th percentile of the ratio between the final outcome and the estimate, which is the range within which nine in ten of the projects in the class ended. The thick bar covers the middle half of the projects, from the 25th to the 75th percentile, with a tick at the median. Each row also gives the number of projects in the class and the percentiles named at the head of the columns.
A ratio of 1.00 means that a project ended on its estimate. For cost and schedule a ratio above 1.00 means that the project cost more or took longer than estimated. For benefits a ratio below 1.00 means that the project delivered less than estimated. Each ratio compares the final outcome with the estimate made at the final investment decision, with costs adjusted for inflation.
Cost and schedule are drawn on a logarithmic scale, on which a doubling has the same width anywhere along the axis. Benefits are drawn on a linear scale because the 5th percentile for IT is below zero, which a logarithmic scale cannot show.
The rows follow the order of the book's tables. Sorting by median places the class with the lowest median ratio first.
Sources
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Appendix 2, Tables A2.1 to A2.3.
The Portfolio Game
From my current research, not yet peer-reviewed
What you will learn How choosing the proposals with the best estimated ratios of benefit to cost tends to produce a portfolio that costs more than estimated, although no estimate is biased, and how much of that difference remains when each new estimate is multiplied by an uplift taken from that experience.
You act as an investment committee with ten proposals and a budget of 500 million. Fund the proposals you prefer and reveal their final costs, which the game compares with the amount you committed and with a choice made at random.
Round 1 Fund proposals within the budget
Committed 0 of 500 million 500 million left
Costs and benefits are in million. Each ratio is the benefit divided by the estimated cost.
Round 1 Final costs of the ten proposals
Final cost divided by estimate, for the ten proposals ranked by estimated benefit-cost ratio (highest at the top)
- Funded
- Not funded
- Final cost equals the estimate
The ten proposals in numbers
| Proposal | Benefit-cost ratio | Estimate (million) | Final cost (million) |
|---|
Amounts are in million and the proposals are in the order of the chart. The final cost of a proposal that was not funded is what it would have cost.
How it works
Each proposal has a true cost between 60 and 200 million and a benefit between 1.05 and 1.60 times that cost, both fixed when the ten proposals are dealt. The estimate you see is the true cost multiplied by a random error. The errors are scaled so that an estimate equals the true cost on average, which is the sense in which no estimate is biased. Benefits are shown at their true value, which leaves the cost error as the only source of error in the ranking.
The size of an error depends on the type of project. For each type, the game takes the spread of the errors from a reference class, which is a group of past projects of the same type whose actual costs are known. The classes come from Hubbard, Budzier and Leed (2025), who report the ratio of actual to estimated cost in each class at five percentiles from the 5th to the 95th. The game uses the 26 cost classes that hold at least 30 projects, interpolates between the percentiles and draws from each distribution between its 3rd and its 97th percentile. A reactor upgrade therefore has a wider range of errors than a solar park. Treating the spread of a class as the size of the estimating error is a simplification of the game.
The uplift of round two is the final cost of your first portfolio divided by its committed total. Round two deals ten new proposals and multiplies each estimate by that number, so that the uplift is tested on proposals it was not calculated from. The comparison with a random choice is the average over each possible set of the same number of proposals from the same deal, whether or not the set fits the budget.
The simulated figures come from 2,000 games of the same model, in which a committee goes through the proposals in the order of their estimated ratio and funds each one that still fits the budget. A second round follows when the uplift from the first round is at least 1.01. The figures are calculated in your browser from a fixed starting number, so that they are the same on each visit. The final cost of round two still exceeds the committed total on average, mainly because the uplifted estimates let fewer proposals fit the same budget, which makes the selection stricter.
Eliasson and Fosgerau (2013) set out a stylised model in which each project has a payoff, which can be any measure that influences the decision to implement the project. At the time of the decision only a prediction of the payoff is known, which contains an error. A project is more likely to be selected the higher its predicted payoff. They prove under general assumptions that the predicted payoff of the selected projects exceeds their actual payoff on average, although the predictions are unbiased across all candidate projects, and that the difference increases when the selection becomes stricter. In their simulations they apply unbiased random errors to the costs and benefits of 461 road and rail investments that competed for inclusion in the Swedish transport investment plan for 2010 to 2021 and select the investments with the highest estimated benefit-cost ratios. The costs of the selected investments are then underestimated and their benefits overestimated on average, by more the larger the errors, the smaller the share of investments that is selected and the more similar the investments are. They note that the same uplift applied to all projects does not change which projects are selected when the number selected is held constant, and that uplifts can still make aggregate budgets more accurate when the size of the difference is known from experience. The authors add that their result does not rule out bias in the estimates.
The game is a small version of the selection problem in my current research, in which a decision-maker with a fixed budget ranks proposals by estimated benefit-cost ratio and funds from the top. That research, which is not yet peer-reviewed, examines how noise in cost and benefit estimates affects which projects are selected and how the selected projects perform against those estimates. It also argues that an uplift calibrated on the outcomes of funded projects raises the bar of a rule that requires a ratio above 1 by more than the bias in the estimates warrants. Where the uplift lowers ratios to below 1, round two reports how many, which is that effect in a game whose estimates are unbiased.
The mechanism is also the subject of Noise and Selection. The classes that the errors are taken from can be explored in Reference Classes.
Sources
- Eliasson, J. and Fosgerau, M. (2013). Cost overruns and demand shortfalls – Deception or selection? Transportation Research Part B, 57, 105–113.
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Appendix 2, Table A2.1.
Nature in the Business Case
From my current research, not yet peer-reviewed
What you will learn How much a change in the ecological quality of nature near homes adds to or takes from a project's net present value, and how large the change must be for the net present value to change sign.
Enter a project's costs and other benefits, the homes near the nature it changes and the change in their bioscore, the Danish national index of ecological quality. The chart shows the net present value without and with a nature term, which is that change valued at the price difference found among Danish homes of the same type in the same parish.
The starting value is the median sale price in my data.
The average change in the bioscore within 1 kilometre of those homes, from −1 to 1 point. A negative value is a loss of ecological quality.
Net present value by the change in the bioscore (€ million)
- With the nature term
- 95% interval
- Without the nature term
- Beyond the typical difference
The research behind the estimate is on the Biodiversity page. The Sorting Machine shows how a comparison within parishes differs from a comparison across all homes.
How it works
The estimate
My current research matches Danish home sales from 2015 to 2025 to the bioscore, the index of the national Biodiversitetskort. The index runs from 0 to 19 on a national grid of 10-metre squares and is built from records of red-listed species and from indicators of their habitats (Ejrnæs et al. 2021). My research uses the average score within 1 kilometre of a home as a measure of the ecological quality of the nature around it.
Among homes of the same type in the same parish, one additional bioscore point within 1 kilometre is associated with about percent higher prices, with a 95 percent interval from to percent. My research states its prices in Danish kroner, which the tool converts to euro at kroner per euro, the rate used in the research.
The calculation
The net present value of a project is the present value of its benefits minus the present value of its costs (Boardman et al. 2018). A present value is the sum of the amounts of each year, each discounted to its worth today.
The nature term is the number of homes times their average price times the share of the price that corresponds to the change in the bioscore.
nature term = homes × average price × (e × change − 1)
The net present value with the nature term is the other benefits minus the costs plus that term. For a single project compared with the status quo, the rule in Boardman et al. (2018) is to adopt the project if its net present value is positive. The switching value is the change in the bioscore at which the net present value with the nature term is zero. The name follows HM Treasury (2026), where a switching value is the value that a key variable would need to change to for an option to stop representing value for money.
The 95 percent interval repeats the calculation at the two ends of the interval of the estimate. It covers the statistical uncertainty of the estimate and leaves out the uncertainty in the values entered above. The nature term is a single change in the value of the homes, so it enters the net present value once and is not discounted as a yearly flow.
The tool shows no benefit-cost ratio, the benefits divided by the costs, because Boardman et al. (2018) recommend that analysts avoid ranking policies by that ratio and rely on net benefits. One of their reasons is that the ratio changes when a loss is added to the costs where it could have been subtracted from the benefits, while net benefits stay the same.
Where the change in the bioscore comes from
The tool does not calculate the change, which follows from the land that the project alters. The bioscore within 1 kilometre of a home is the average score across the circle of 314 hectares around it. If 20 hectares in that circle fall from a score of 4 to a score of 0, the average falls by 20 ÷ 314 × 4, which is about 0.25 points, for a home whose circle contains all of that land.
Where the estimate applies
My research applies the estimate to changes of the size found between homes in the same parish, which typically differ by points, and to changes that affect few homes compared with the housing market. Half of the homes sold have a bioscore below within 1 kilometre and 95 percent have less than . The tool therefore covers changes of up to 1 point. It applies the same percentage per point at each level of the bioscore, which my research estimates as an average across the homes sold.
If the other benefits already include a value for the same nature, for example for recreation near the homes, adding the nature term counts part of that value twice.
The Danish guidance on cost-benefit analysis (Finansministeriet 2023) gives the relation between house prices and an environmental good as an example of how a good with no market price can be valued. It asks for effects that cannot be valued to be listed beside the calculation.
Sources
The estimate, its interval and the figures on the homes sold come from my current research, which is not yet peer-reviewed and may change.
- Boardman, A. E., Greenberg, D. H., Vining, A. R. and Weimer, D. L. (2018). Cost-Benefit Analysis: Concepts and Practice. Fifth edition. Cambridge University Press.
- Ejrnæs, R., Bladt, J., Moeslund, J. and Brunbjerg, A. K. (2021). Biodiversitetskortets bioscore. Videnskabelig rapport fra DCE nr. 456. Aarhus Universitet, DCE – Nationalt Center for Miljø og Energi.
- Finansministeriet (2023). Vejledning i samfundsøkonomiske konsekvensvurderinger. Finansministeriet.
- HM Treasury (2026). The Green Book: UK Government Guidance on Appraisal. HM Treasury.
Nature Next Door
From my current research, not yet peer-reviewed
What you will learn How much the price of a home differs with the ecological quality of the nature within 1 kilometre, in percent and in euro, and how wide the uncertainty around that figure is.
Set a change in the bioscore, the Danish national index of ecological quality, and the price of a home. The tool shows the price difference that my current research finds between homes of the same type in the same parish whose bioscores differ by that much, with its 95 percent interval.
From −1 to 1 point. Homes of the same type in the same parish typically differ by points.
The starting value is the median sale price in my data.
Price difference in euro by the change in the bioscore, at a home price of
- Estimate
- 95% interval
- Your change
- Beyond the typical difference
The research behind the estimate is on the Biodiversity page. Nature in the Business Case applies the same figure to the homes near a project.
How it works
The estimate
My current research matches Danish home sales from 2015 to 2025 to the bioscore, the index of the national Biodiversitetskort. The index runs from 0 to 19 on a national grid of 10-metre squares and is built from records of red-listed species and from indicators of their habitats (Ejrnæs et al. 2021). My research uses the average score within 1 kilometre of a home as a measure of the ecological quality of the nature around it.
The figure is a hedonic price, which is the price of one feature of a home recovered from the sale prices of whole homes. Each home is compared with homes of the same type in the same parish, with characteristics such as its size, age and energy label, its distance to the coast and to a station, noise and the greenness of its surroundings held constant. One additional bioscore point is then associated with about percent higher prices, with a 95 percent interval from to percent.
From percent to euro
The percentage is the estimate times the change in the bioscore. The euro figure applies it to the home price as a compound rate, the price times (e × change − 1), which is how my research arrives at about per point at the median sale price of . My research states its prices in Danish kroner, which the tool converts to euro at kroner per euro, the rate used in the research.
Where the estimate applies
Half of the homes sold have a bioscore below within 1 kilometre and 95 percent have less than , against an average of . My research applies the estimate to differences of the size found between homes of the same type in the same parish, which typically differ by points. The tool therefore covers changes of up to 1 point, which is times that typical difference. It applies the same percentage per point at each level of the bioscore, which my research estimates as an average across the homes sold.
The estimate by distance
The table shows the estimate when the bioscore is measured in circles of other sizes around the home. Circles up to 1 kilometre give between and percent per point, with overlapping intervals from 250 metres to 1 kilometre. A circle of 2 kilometres gives about percent, while the estimate for 5 kilometres cannot be distinguished from zero.
| Circle around the home | Estimate per bioscore point |
|---|
Sources
The estimate, its interval and the figures on the homes sold come from my current research, which is not yet peer-reviewed and may change.
- Ejrnæs, R., Bladt, J., Moeslund, J. and Brunbjerg, A. K. (2021). Biodiversitetskortets bioscore. Videnskabelig rapport fra DCE nr. 456. Aarhus Universitet, DCE – Nationalt Center for Miljø og Energi.
The Value of a Tonne of Carbon
What you will learn How the values that United States government bodies have published for a tonne of carbon dioxide depend on the discount rate and the year of emission, and at which value the result of an appraisal changes sign.
The social cost of carbon is the present value of the damages that one extra tonne of carbon dioxide causes in each future year. Choose a set of published estimates, a discount rate and a year of emission, and then enter a project to see the carbon value at which its net present value reaches zero.
Step 1 How the value is set
The discount rate is the yearly rate at which a future amount is reduced to its value today. A lower rate therefore gives damages in the distant future more weight.
Value of one tonne of carbon dioxide at each of the three discount rates, in 2020 US dollars
- All values are in 2020 US dollars per metric tonne of carbon dioxide and are shown as published, without interpolation between rates or years.
- The two sets differ in how they discount and in their models of the economy, the climate and the damages. The 2021 set holds each rate constant, while in the 2023 set the rate falls over time and the rate shown is its average over the first ten years. For that reason the tool compares values within one set only. For a tonne emitted in 2020, a rate of 2.5 percent gives $76 in the 2021 set and $120 in the 2023 set.
- In January 2025 an executive order disbanded the working group behind the 2021 estimates and withdrew its documents as no longer representative of government policy. Guidance of May 2025 from the Office of Management and Budget states that it is no longer federal policy to maintain a uniform estimate of the monetised impacts of greenhouse gas emissions. Both sets are shown here for how they respond to the discount rate and the year of emission.
Step 2 When it changes a decision
The switching value is the carbon value at which the net present value of a project reaches zero. The numbers below are an invented example, which you can replace with your own.
The net present value is the sum of the discounted benefits of a project minus the sum of its discounted costs, here before the carbon effect is counted.
A positive number is an increase and a negative number is a reduction.
Net present value of the project by the value placed on a tonne of carbon dioxide
- Net present value
- The three values chosen in step 1
- Switching value
The talk The Value of a Tonne of Carbon covers where the official values come from.
How it works
Step 1 looks up published values and calculates nothing. Each number is the value that the source prints for that discount rate and that year of emission. The values of both sets are averages across the models that each source uses. The 2021 source also prints a fourth value, the 95th percentile at 3 percent, which the tool leaves out.
Step 2 multiplies the yearly change in emissions by the sum of the discount factors of the years, which gives the discounted tonnes. The net present value with the carbon effect is the value without it minus the carbon value times the discounted tonnes. The switching value is the value without the carbon effect divided by the discounted tonnes.
Sources
- US Environmental Protection Agency (2023). Report on the Social Cost of Greenhouse Gases: Estimates Incorporating Recent Scientific Advances. Table ES.1.
- Interagency Working Group on Social Cost of Greenhouse Gases, United States Government (2021). Technical Support Document: Social Cost of Carbon, Methane, and Nitrous Oxide. Interim Estimates under Executive Order 13990. Table ES-1.
- Executive Order 14154 of 20 January 2025, Unleashing American Energy. Federal Register, volume 90, number 18, 29 January 2025.
- Office of Management and Budget (2025). Memorandum M-25-27, Guidance Implementing Section 6 of Executive Order 14154, Entitled “Unleashing American Energy”. 5 May 2025.
Long-Lived Assets
What you will learn What the later decades of an asset’s life count for in an appraisal and how likely a rare event is over that life.
Road and rail bridges have an indicative design life of 100 years under the European structural design standard, while the United Kingdom and Sweden appraise infrastructure over 60 years. Choose a year and a rare event below to see what each means for an asset that lasts that long.
Part 1 What the later decades count for
The year is counted from today. An appraisal discounts a later dollar at an official yearly rate, which gives its present value, the amount that the dollar counts for today.
Present value of one dollar received in a later year, in cents
- Germany, 1.7 percent
- United Kingdom, 3.5 percent falling to 2.5
- Japan, 4 percent
- United States, 7 percent
- The year you chose
Part 2 The chance of a rare event over a lifetime
The tool opens at 200 years because European insurers must hold capital against a loss that occurs once in 200 years.
Chance that the event occurs at least once, by the life of the asset
The talk Tipping Points & Tail Risk for Long-Lived Assets covers this material in more depth.
How it works
The present value of one dollar received in a later year is one divided by one plus the discount rate, raised to the power of the number of years. Where the rate changes after a number of years, as the British rate does, the factors of the periods are multiplied.
The chance that an event occurs at least once during the life of an asset is one minus the chance that it occurs in none of the years. For an event that occurs on average once in R years and an asset that lasts L years, that is 1 − (1 − 1/R)L.
Sources
- Design lives are the indicative values of the European standard EN 1990, as summarised in the slides of Gulvanessian (2008), EN 1990: Eurocode: Basis of Structural Design.
- Appraisal periods are from HM Treasury (2026), The Green Book, and Trafikverket (2024), ASEK 8.0.
- Discount rates are from PTV, TCI Röhling & Mann (2016), the method handbook for the German federal transport plan 2030, from HM Treasury (2026), from the technical guideline for cost-benefit analysis of public works of the Japanese Ministry of Land, Infrastructure, Transport and Tourism (2025) and from Circular A-94 of the United States Office of Management and Budget (1992), which its memorandum M-25-23 reinstated in 2025.
- The 1-in-200-year standard is Article 101 of Directive 2009/138/EC, as described by Trust et al. (2025), Planetary Solvency.
- The sea level projection is from IPCC (2023), AR6 Synthesis Report, Summary for Policymakers.
Calibration Quiz
What you will learn How often the true value falls inside the ranges that you state with 90 percent confidence.
For each of ten questions, give a lower and an upper bound that you are 90 percent sure contain the true value. After the tenth answer a plot shows each of your ranges against the true value.
Your result
Your ten ranges and the true values
- Your range, true value inside
- Your range, true value outside
- True value
How it works
Ranges stated with 90 percent confidence are calibrated when nine in ten of them contain the true value over many questions. On ten independent questions the number inside varies by chance around nine. My calculation from the binomial distribution gives all ten in about 35 of 100 quizzes, nine in about 39, eight in about 19 and seven or fewer in about 7.
The questions are in different units, which is why each row of the plot has its own scale. The scale of a row is set so that your range fills the same bar in each row. The mark then shows where the true value lies relative to your range, up to one range width on either side.
The exercise follows the test in Chapter 6 of How to Measure Anything in Project Management, which asks for a 90 percent range on each of ten questions of its own. The book reports that Douglas Hubbard has given tests of this kind to more than 3,000 people over 25 years. In the initial benchmark tests, 56 percent of the 90 percent ranges that people stated for trivia questions contained the correct answer. The book also reports that, once enough questions have been answered to allow for chance, 80 percent of participants are calibrated after the fifth exercise of the training, another 15 percent improve significantly without reaching that level and 5 percent show no significant improvement.
The true values come from the publications listed below. Where a publication gives a best estimate with an uncertainty range, the quiz uses the best estimate. The questions are the same on each visit, which means that a second attempt also measures what you remember.
Sources
- CGTN (2020). Three Gorges Project gets ‘completion acceptance’. 1 November 2020. Question 6.
- Frank, E. & Sudarshan, A. (2024). The Social Costs of Keystone Species Collapse: Evidence from the Decline of Vultures in India. American Economic Review 114(10), 3007–3040. Question 10.
- Gulvanessian, H. (2008). EN 1990: Eurocode: Basis of Structural Design: The Key Head Eurocode. Presentation at the workshop EU-Russia Cooperation on Standardisation for Construction, Moscow, 9–10 October 2008. Question 5.
- HM Treasury (2026). The Green Book: UK Government Guidance on Appraisal. Question 9.
- Hubbard, D. W., Budzier, A. & Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Question 4 and the results of calibration tests and training.
- IPCC (2021). Summary for Policymakers. In Climate Change 2021: The Physical Science Basis. Contribution of Working Group I to the Sixth Assessment Report of the Intergovernmental Panel on Climate Change. Cambridge University Press. Questions 3 and 8.
- Kahneman, D., Sibony, O. & Sunstein, C. R. (2021). Noise: A Flaw in Human Judgment. William Collins. Question 7.
- Museums of History NSW (undated). Sydney Opera House guide. Question 1.
- US Government Accountability Office (2022). NASA: Assessments of Major Projects. GAO-22-105212. Question 2.
Monte Carlo Simulator
What you will learn How a list of uncertain risks adds up to a spread of possible total costs, from which the chance of exceeding a budget can be read.
Enter a base cost, a budget and a list of risks, each with the probability that it occurs and a 90 percent range for its cost. The simulator draws 10,000 possible outcomes of the project and shows how often the total cost exceeds the budget and which risks account for most of the spread.
The cost of the project if none of the risks occurs.
The amount that the total cost is compared with.
| Risk event | Probability (%) | Lower bound (million) | Upper bound (million) | Remove |
|---|
The table opens with an invented example and holds up to six risks. A 90 percent range is wide enough that you are 90 percent sure the cost would fall inside it if the event occurs.
Total cost in 10,000 simulated outcomes
- At or below the budget
- Above the budget
- Budget
- No risk event occurred
Share of the spread in total cost by risk
Two related tools in the Lab are the Calibration Quiz, which gives practice in setting 90 percent ranges, and Risk Matrix Roulette, which looks at the scoring method that this model replaces.
How it works
A Monte Carlo simulation is a way of doing arithmetic with numbers that are uncertain, by trying a large number of random cases. For each of 10,000 possible outcomes of the project, the simulator decides at random whether each risk event occurs, using the probability in the table, and draws a cost for each event that occurs. The total cost of an outcome is the base cost plus the costs drawn. Taken together, the 10,000 totals show which total costs are possible and how often each of them occurs.
The model is the simple quantitative risk model in Chapter 5 of Hubbard, Budzier and Leed (2025). It replaces the scores of a risk matrix with a probability and a 90 percent range for each risk and adds the risks up in 10,000 simulated scenarios. The book presents the sum as a loss exceedance curve, which gives for each amount the share of scenarios with a larger loss. This tool covers the cost of each risk and leaves out the effect on the schedule, which the spreadsheet that accompanies the book also simulates. It adds a base cost to the simulated losses and compares the total with one budget.
The cost of an event that occurs is drawn from a lognormal distribution whose 5th and 95th percentiles are the two bounds in the table. Nine draws in ten therefore fall inside the range, one in twenty falls below the lower bound and one in twenty falls above the upper bound. The book uses this distribution for the impact of risk events because it gives no cost of zero or less and allows costs well above the upper bound.
The logarithm of the cost follows a normal distribution. The mean of that distribution lies midway between the logarithms of the two bounds, while its standard deviation is the distance between those logarithms divided by 3.29, the width of the central 90 percent of a normal distribution measured in standard deviations.
In symbols, with C for the cost, L for the lower bound and U for the upper bound, the model reads
\[ \begin{aligned} \ln C &\sim N\!\left(\mu,\ \sigma^{2}\right) \\[0.35em] \mu &= \frac{\ln L + \ln U}{2} \\[0.35em] \sigma &= \frac{\ln U - \ln L}{3.29} \end{aligned} \]The risks are drawn independently of each other, which means that the occurrence or the cost of one event has no influence on another. Risks that share a cause on a real project occur together more often than independent draws allow, which makes large totals more likely than the chart shows.
The median is the total cost that half of the outcomes do not exceed. The tile for 90 percent gives the total cost that nine outcomes in ten do not exceed. Spread in the second chart is measured by the variance, which is the average squared distance of the outcomes from their mean. Because the risks are drawn independently, the variance of the total cost is the sum of the variances of the individual risks, which gives each risk a share of the spread.
The result that shows when the tool opens uses a fixed sequence of random numbers, which keeps it the same on each visit. Each press of Run simulation draws new random numbers, which is why the results differ a little from run to run. With 10,000 outcomes the share above the budget is accurate to about one percentage point. Because the base cost and the budget are not random, a change in either is applied to the same 10,000 outcomes without a new run.
Sources
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Chapter 5, Project Uncertainty and Risk: A Primer, and Appendix 3, Selected Distributions.
Value of Information
What you will learn What a measurement is worth before a decision is taken, and why its value depends on how close the estimate lies to the break-even value.
Enter the range that you are 90 percent sure contains the benefit of a project, together with the benefit at which the project breaks even. The tool shows how likely a decision taken on that estimate is to be wrong and the most that a measurement is worth.
Distribution of the benefit (million)
- Your uncertainty about the benefit
- Outcomes in which proceeding is wrong
- Break-even value
The Calibration Quiz lets you practise setting a range that you are 90 percent sure of.
How it works
The expected value of perfect information is the most that a risk-neutral decision maker should pay to remove all uncertainty about one quantity before a decision is taken. A risk-neutral decision maker considers only the probability-weighted average of the outcomes. The value is calculated as the chance that the decision taken on the current estimate turns out to be wrong, multiplied by the average loss when it does.
The idea is introduced in Chapter 4 of How to Measure Anything in Project Management (Hubbard, Budzier and Leed, 2025). Chapter 8 of the book sets out the method, which this tool applies to one uncertain quantity. The default decision is to proceed when the expected benefit is above the break-even value and to reject the project otherwise. That decision is wrong when the benefit falls on the other side of the break-even value, in which case the loss is the distance between the two.
The tool reads the two bounds as the 90 percent interval of a normal distribution, which places the expected benefit halfway between them and gives a standard deviation equal to the width of the interval divided by 3.29. The book recommends that distribution where a result above the expected value is as likely as one below it and any absolute limits lie far outside the two bounds. For a normal distribution the calculation reduces to one formula. With \(\mu\) for the expected benefit, \(\sigma\) for the standard deviation and \(T\) for the break-even value,
\[ \begin{gathered} \mathrm{EVPI} = \sigma\,\bigl[\varphi(z) - z\,\Phi(-z)\bigr] \\[0.4em] z = \frac{|\mu - T|}{\sigma} \end{gathered} \]where \(\varphi\) is the density and \(\Phi\) the cumulative probability of the standard normal distribution. The formula multiplies the standard deviation by a factor that depends only on the number of standard deviations between the expected benefit and the break-even value. The value is highest when the two are equal, where it amounts to about 0.4 standard deviations, and falls towards zero as the distance between them grows.
A measurement that halves the uncertainty leaves an interval half as wide around an estimate that is not yet known. The tool values such a measurement with the same formula, in which the standard deviation of that future estimate, 0.87 times \(\sigma\), takes the place of \(\sigma\). This assumes a measurement whose error follows a normal distribution.
The tool counts each million of benefit above or below the break-even value as one million gained or lost. It treats the benefit as the only uncertain quantity, whereas in a full business case the break-even value depends on other quantities that are uncertain as well.
In a full business case the book repeats the calculation for each uncertain quantity to find the ones worth measuring. It reports that when the firm of Douglas Hubbard computed information values in the decision models of more than 200 major projects, the quantities that clients had spent the most time measuring were, on average, those with the lowest information value, a pattern that Hubbard calls the measurement inversion.
Sources
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Chapter 4, Chapter 8 and Appendix 3.
Risk Matrix Roulette
What you will learn A risk matrix can give one rating to risks whose expected losses differ several times over and can rank two risks in a different order when one category boundary is moved.
A risk matrix places each risk in a cell according to a likelihood category and an impact category and gives the cell a rating such as Low, Medium or High. Over three short rounds the game compares those ratings with the expected loss of each risk, which is its probability multiplied by its impact.
Round 1 of 3 A number for a likelihood word
A risk register describes a risk as unlikely. Set the probability that you take the word to mean, then compare.
Risk A has a probability of 48 percent. Move the boundary below that value and watch where the matrix places A.
Probabilities attached to the word “unlikely” (%)
Risk X and risk Y in a five by five risk matrix, impact in million
- Low, score 1–4
- Medium, 5–12
- High, 15–25
- Your boundary
| Probability | Impact if the risk occurs (million) | ||||
|---|---|---|---|---|---|
Expected loss of the six risks that the matrix rated Medium (million)
The matrix rates both risks Medium. Pick the one with the larger expected loss.
The book proposes to replace the likelihood rating of a risk with an explicit probability and the impact rating with a 90 percent confidence interval for the loss. You can practise such estimates in the Calibration Quiz and add up risks described in that way in the Monte Carlo Simulator.
How it works
In the survey for How to Measure Anything in Project Management, the book I co-authored, a risk matrix had been used in 107 of the 215 projects, more than any other tool for assessing uncertainty and risk that the survey asked about.
The matrix in this game follows the example in Chapter 5 of that book. Likelihood and impact each have five categories numbered 1 to 5. The score of a cell is the product of the two numbers, with scores of 1 to 4 rated Low, 5 to 12 Medium and 15 to 25 High. I chose the category limits for this game, with each category including its upper limit, and constructed the eight risks to fit them.
Expected loss is the probability of a risk multiplied by its impact, which gives 1.2 million for a 40 percent chance of losing 3 million. The book uses this measure to demonstrate the loss of resolution in a matrix and notes that it is more tolerant of risk than most decision-makers are, which makes the comparison lenient towards the matrix.
Round 1 follows the discussion of verbal labels in that chapter, which reports one study in which 23 NATO officers gave the word “unlikely” probabilities from 5 to 35 percent and another, by the psychologist David Budescu and two co-authors, in which the answers ranged from 8 to 66 percent.
Round 2 shows what Cox (2008) calls range compression, in which a matrix assigns identical ratings to quantitatively very different risks. In the example matrix of the book, the expected losses inside one cell differ by a factor of 100 between the lowest and the highest combination of likelihood and impact. One point is given for each pair in which your answer matches the expected losses. In the third pair the two are equal, which makes “About equal” the matching answer.
Round 3 moves one category limit and leaves the two risks as they are. Thomas, Bratvold and Bickel (2014) varied the category limits of a matrix from the oil and gas industry and found that the ranking of three outcomes changed with the limits in three of the four cases they tested. Cox (2008) shows more generally that a matrix can assign a higher rating to a quantitatively smaller risk.
Sources
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Chapter 5 and Appendix 1.
- Cox, L. A., Jr. (2008). What’s Wrong with Risk Matrices? Risk Analysis, 28(2), 497–512.
- Thomas, P., Bratvold, R. B. and Bickel, J. E. (2014). The Risk of Using Risk Matrices. SPE Economics & Management, 6(2), 56–66.
Parade of Trades
What you will learn How variation in the weekly output of trades that depend on each other can delay a project in which each trade has the planned capacity on average.
Five trades work through the 35 rooms of a building one after another, each completing as many rooms in a week as the roll of a die allows and the trade before it has finished. Play a project first, to see in which week the last room is finished against a plan of 14 weeks and where a trade had capacity and no room to work on.
Die that each trade rolls (each die averages 3.5 rooms a week)
The building of 35 rooms, each filled from the bottom by the five trades from Civil to Commissioning
- Completed, one layer for each trade
- Ready for the next trade
- Capacity lost this week
- Where the plan expects each trade
Week 0of 14 planned
0 of 35 rooms finished
0 rooms of capacity lost
In the order of the layers, the rows show for each trade the rooms waiting when it rolled, its roll, the rooms it has completed, and the capacity it has used (in its own colour) and lost (in gold).
Step 2 The same project 10,000 times with each die
Because a single project can be lucky or unlucky, the simulation plays 10,000 projects with each of the three dice and counts the week in which each one finishes.
Share of 10,000 simulated projects that finish in each week (percent)
- Share of projects
- Median project
- Plan, week 14
- Your project
Step 3 One measure for the same project
Suppose that the regular die describes your trades, that the project is running later than its plan and that the last trade stands idle much of the time. Choose the one measure that you would take to see what each of the four does to the finishing week in the simulation.
Finishing week of 10,000 simulated projects, unchanged and with each measure
- 5th to 95th percentile
- Average
- Plan, week 14
- Average of the unchanged project
How it works
The game is described in Chapter 7 of How to Measure Anything in Project Management. A building has 35 rooms through which five trades pass in a fixed order. The book lists them as civil construction, mechanical equipment, electrical and instrumentation work, fit-out and commissioning. Each week each trade rolls a die. The number it rolls is its capacity for the week. The work it does is the smaller of that capacity and the number of rooms waiting for it. In the book the die travels backward through the chain, from commissioning to civil construction, which means that a room finished by one trade in a week is ready for the next trade in the following week.
The plan uses the average roll. A regular die averages 3.5, which gives each trade 10 weeks for the 35 rooms. Because each trade starts one week after the trade before it, the plan finishes in week 14. The navy dashed line in the building shows where this plan expects each trade to be in the week on screen.
When a trade rolls more than the rooms waiting for it, the difference is capacity that it cannot use and cannot save for a later week. The tool counts this lost capacity in rooms. Capacity that a trade rolls before the first room has reached it counts as lost, because each trade in the game of the book rolls in each week from the first. Capacity beyond the last room of the building does not count. The share of capacity used is the number of rooms a trade has completed divided by the capacity it has rolled. The plan itself has each later trade wait for its first rooms, which is why a die with 3.5 on each side would still leave the last trade using 71 percent of its capacity.
The three dice are taken from the book. The regular die has the sides one to six. The die that this page calls the steady die has five sides with a three and one side with a six. The third, which the book calls the extreme die, has two zeros, one three and three sixes. Each of them averages 3.5. The book measures the spread of a die by its standard deviation and gives 1.22 for the steady die, 1.87 for the regular die and 2.95 for the extreme die, which are the values of the sample formula for the six sides.
The comparisons play 10,000 projects with each die and with each measure. The random numbers start from a fixed value, so that the figures are the same on each visit. The book reports that its simulated projects usually finish in 16 weeks with the steady die, 18 weeks with the regular die and 21 weeks with the extreme die. In the simulation on this page the most frequent finishing weeks are 16, 18 and 22, with week 21 almost as frequent as week 22 for the extreme die. The averages are 15.9, 18.6 and 22.2 weeks.
The book draws a second lesson from the game, which concerns utilisation. The trades later in the chain use about half of their capacity, which can prompt a proposal to reduce their crews. The book warns that this would prolong the project, because trades whose inputs and outputs vary are short-handed when a batch of rooms arrives. Its advice is to find where the variation in weekly output arises and to reduce it.
The book adds an account from a work site. Edward Zaayman, a project manager and consultant who introduced the authors to the game, describes the welding of a pipeline in a power plant in South Africa, where the welding was behind schedule. The natural reaction, in his words, is to get more welders. He found that the welders were quite predictable and that the step before welding, the rigging of the pipes, was much more uncertain. His solution to speeding up the welding was to make the rigging more predictable, for example by having the same number of crews on site each day.
Sources
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Chapter 7, Cost and Schedule Measurements, section Parade of Trades, with Figures 7.3 and 7.4.
Probability Words
What you will learn How differently people read the same probability word, even when the word has a numerical definition.
Set the probability that you read into each of four words. You then see the lowest and the highest answer each word received in an experiment, next to the definition that the Intergovernmental Panel on Climate Change (IPCC) gives it.
A slider that you leave untouched counts as no answer.
Probability read into each word, in percent
- Lowest to highest answer in the experiment
- IPCC definition
- Your number
Risk Matrix Roulette deals with risk matrices, some of which label their likelihood scale with words of this kind.
How it works
The four words belong to the likelihood scale of the Intergovernmental Panel on Climate Change (IPCC), which gives each word a numerical definition. In the panel’s 2021 report, very likely stands for a probability of 90 to 100 percent, likely for 66 to 100 percent, unlikely for 0 to 33 percent and very unlikely for 0 to 10 percent.
The answers come from an experiment by the psychologist David Budescu and two colleagues, published in 2009. Participants read sentences from an IPCC report and assigned a numerical probability to the words in them. They had been informed of the definitions in that report, which set the same thresholds as the 2021 report. Hubbard (2020) reports the lowest and the highest of all answers for each word and the share of answers that fell outside the definition.
| Word | IPCC definition | Lowest to highest answer | Share outside |
|---|
The book How to Measure Anything in Project Management discusses the experiment in its chapter on project uncertainty and risk. Its point is that people who agree to call a risk unlikely can have different probabilities in mind, which Budescu called the illusion of communication. The book adds that participants who went outside a definition may have disagreed with the label or with its definition. The same chapter describes a study in which 23 NATO officers read “highly likely” as anything from 50 percent to nearly 100 percent.
Your own number counts as inside a definition when it lies within the IPCC range for the word, with the end points included.
Sources
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Chapter 5, Project Uncertainty and Risk: A Primer.
- Hubbard, D. W. (2020). The Failure of Risk Management: Why It’s Broken and How to Fix It (second edition). Wiley. Exhibit 8.3.
- IPCC (2021). Summary for Policymakers. In Climate Change 2021: The Physical Science Basis. Contribution of Working Group I to the Sixth Assessment Report of the Intergovernmental Panel on Climate Change. Cambridge University Press. Footnote 4.
Few Trials, Zero Failures
What you will learn Why a short run of trials without a failure does not show that the failure rate is low, and how two simple rules turn such a run into an estimate and an upper bound.
Pick an example or enter your own number of trials and failures. The chart shows which failure rates remain plausible, with an estimate for the next trial and the highest rate that the trials do not rule out.
Examples (failures in trials)
A trial is one comparable case that could have failed, such as a completed project or an inspection. A failure is the outcome in question, such as a breach of contract or a safety incident.
Knowledge before the trials
Each failure rate from 0 to 100 percent counts as equally plausible before the trials.
How plausible each failure rate is before and after the trials
- After the trials
- Before the trials
With 8 trials and no failure, the observed failure rate is 0 percent, while the rule of succession estimates the probability of a failure in the next trial at 10 percent. The result is compatible with a failure rate of up to 31.2 percent, the 95 percent upper bound, which the rule of three puts at 3 divided by 8, or 37.5 percent. The bound falls below 5 percent after 59 trials without a failure.
The estimates side by side
| Measure | Value |
|---|---|
| From the trials alone | |
| Observed rate Failures divided by trials | 0% |
| Rule of succession Failures plus 1, divided by trials plus 2 | 10% |
| 95% upper bound Highest rate at which so few failures still occur 5 times in 100 | 31.2% |
| Rule of three Shortcut for that bound when no failure has occurred, 3 divided by trials | 37.5% |
| From the curve after the trials | |
| 5th percentile The rate lies below it with 5 percent probability | 0.57% |
| Median The rate is as likely to lie below it as above it | 7.41% |
| 95th percentile The rate lies below it with 95 percent probability | 28.3% |
| Mean Estimate for the next trial | 10% |
How it works
The calculation uses the binomial model, in which each trial fails with the same unknown probability and the trials do not influence one another. Under that model the observed rate, failures divided by trials, is a weak guide when the trials are few. Zero failures in eight trials give an observed rate of 0 percent, although a failure rate of 10 percent would produce eight trials without a failure about 43 times in 100.
The rule of succession starts from the position that each failure rate from 0 to 100 percent is equally plausible before the trials. After s failures in n trials, the probability that the next trial fails is then the number of failures plus 1, divided by the number of trials plus 2.
\[ P(\text{next trial fails}) = \frac{s+1}{n+2} \]The book introduces this estimate in Chapter 5 as Laplace’s rule of succession. It gives the example of a vendor with eight projects and no breach of contract, for which the rule puts the chance of a breach in the next project at 10 percent when nothing else is known (Hubbard, Budzier and Leed, 2025). The same numbers are the opening case of this tool.
The solid curve in the chart is a beta distribution, which describes the plausibility of each value that a proportion between 0 and 1 can take. Chapter 10 of the book uses this distribution to estimate a proportion from a small sample. With nothing known before the trials, its two parameters are the number of failures plus 1 and the number of trials without a failure plus 1. Its mean then equals the rule of succession. Earlier experience enters in the same way, because the earlier trials and the failures among them are added to the two parameters before the new trials are counted. The two numbers of earlier experience need not be whole, which lets experience that is only partly comparable count at a reduced weight.
The 95 percent upper bound answers a different question and uses the trials alone. It is the failure rate at which a result with so few failures would occur in 5 of 100 repetitions of the trials. A higher rate would make the observed result rarer than that. With no failure in n trials, the bound is the rate at which n trials in a row pass with a probability of 0.05. That probability is the chance that a single trial passes, 1 minus the rate, raised to the power n. Because the natural logarithm of 0.05 is close to minus 3, the solution is approximately 3 divided by n, the shortcut known as the rule of three.
\[ \begin{gathered} (1-p)^{n} = 0.05 \\ p = 1 - 0.05^{1/n} \approx \frac{3}{n} \end{gathered} \]The shortcut lies above the exact bound at each number of trials, by 6.3 percentage points at 8 trials and by less than 1 point from 21 trials. When failures have occurred, the tool solves the same condition numerically for the rate at which that many failures or fewer have a probability of 5 percent. The exact bound and the rule of three follow from the binomial model alone and are not taken from the book.
The 95th percentile in the table and the 95 percent upper bound answer different questions. The percentile describes the failure rate given the trials and the starting position, whereas the bound describes how often such trials would occur at a given rate. With nothing known before the trials, the 95th percentile after n trials equals the exact bound for n plus 1 trials with the same number of failures. Because one more trial without a failure lowers the bound, the percentile in the table then lies below the bound.
Sources
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Chapter 5, Project Uncertainty and Risk: A Primer, and Chapter 10, More Measurement Methods Made Easy.
Noise and Selection
From my current research, not yet peer-reviewed
What you will learn How funding the proposals with the best estimated ratios of benefit to cost can leave the funded projects above their cost estimates on average, even when no estimate is biased.
Set the noise in the estimates (the size of their random errors) and the share of proposals that is funded. The chart shows the average ratio of actual to estimated cost among the funded projects when the estimates are unbiased, which here means that each estimate is as likely to be too high as too low.
At 20, about two estimates in three lie between 18 percent below and 22 percent above the true value.
Proposals are ranked by estimated benefit-cost ratio (benefit divided by cost) and funded from the top.
Average ratio of actual to estimated cost among the funded projects
- Funded by estimated benefit-cost ratio
- Same share funded at random
- Added by selection
- Mean of the reference class
In The Portfolio Game you make the selection yourself and can see the same effect.
How it works
An authority that cannot fund all proposals ranks them by the estimated ratio of benefit to cost and funds from the top of the list. A proposal reaches the funded group more easily when chance made its cost estimate too low or its benefit estimate too high. The funded group therefore contains a larger share of underestimated costs than the full list does, which is why its actual costs lie above its estimates on average even when the estimates of all proposals together are unbiased. Eliasson and Fosgerau (2013) showed that this effect of selection arises whenever forecasts are related to the decision to implement a project. They illustrated it with simulations on the 461 road and rail investments that competed for a place in the Swedish transport investment plan for 2010 to 2021. Neither their result nor this tool rules out that estimates are biased as well.
The calculation assumes that the error of each estimate follows a normal distribution on a logarithmic scale and is as likely to make the estimate too high as too low, that cost and benefit estimates are equally noisy with errors unrelated to each other and that all proposals are equally good. The noise level is the standard deviation of that error, which for moderate values is close to the typical error in percent. Under these assumptions the average ratio of actual to estimated cost among the funded projects has an exact formula, which comes from my current research. It multiplies the average ratio that noise produces without selection by a factor that grows as the share funded falls.
\[ \mathbb{E}\!\left[\frac{C}{\hat{C}}\,\middle|\,\text{funded}\right] = e^{\sigma^{2}/2}\times\frac{1}{\alpha}\,\Phi\!\left(\frac{\sigma}{\sqrt{2}}-\Phi^{-1}(1-\alpha)\right) \]Here C is the actual cost and Ĉ the estimate, σ is the noise level as a decimal (0.20 for 20 percent), α is the share of proposals funded and Φ is the cumulative distribution function of the standard normal distribution.
The first factor is what the line for funding at random shows. It lies slightly above 1.0 because the ratio is not symmetric. An estimate that is 20 percent too low gives a ratio of 1.25, while the equally likely estimate that is 25 percent too high gives a ratio of 0.80, so that the two average to a ratio above 1.0.
The effect grows with the noise, which means that more precise estimates reduce it even when no estimate is biased. With 30 percent of the proposals funded, halving the noise from 20 to 10 percent lowers the figure from 19 to 9 percent above the estimates.
When proposals differ in true quality, the ranking partly reflects quality, so that the funded projects owe less of their place to favourable errors. The effect of selection is then smaller, which the simulations of Eliasson and Fosgerau (2013) also show. The default settings, noise of 20 percent and 30 percent of proposals funded, are the baseline of my current research.
Heckman (1979) showed that a regression fitted only to selected cases omits a term which, for normally distributed errors, depends on each case’s probability of being selected. He proposed estimating that probability from the full sample, including the cases that were not selected, which for projects means records of the proposals that were not funded as well as of the projects that were.
The reference classes come from Appendix 2 of the book, which reports the mean ratio of actual to estimated cost for each class of completed projects, with estimates taken at the final investment decision and costs adjusted for inflation. The comparison is limited to seven classes of infrastructure, since the calculation describes an authority that chooses among appraised proposals.
Sources
- Eliasson, J. and Fosgerau, M. (2013). Cost overruns and demand shortfalls – Deception or selection? Transportation Research Part B, 57, 105–113.
- Heckman, J. J. (1979). Sample selection bias as a specification error. Econometrica, 47(1), 153–161.
- Hubbard, D. W., Budzier, A. and Leed, A. B. (2025). How to Measure Anything in Project Management. Wiley. Appendix 2, Table A2.1.
The Sorting Machine
From my current research, not yet peer-reviewed
What you will learn Why a comparison of homes across the country can show a far larger price difference for the ecological quality of nearby nature than a comparison of homes within the same parish.
Each dot is a simulated home, placed by its price and by the average bioscore within 1 kilometre of it, where the bioscore is a Danish index of ecological quality from 0 to 19. The slider sets the degree of sorting, the tendency of buyers who value nature to settle in the parishes (small local districts) with a high bioscore, which in the simulation raises the price level of those parishes.
The scale runs from 0, where the price level of a parish is unrelated to its bioscore, to 100, where the simulation is calibrated to my current research on Danish home sales.
Price against bioscore for 300 simulated homes in five parishes
- One simulated home
- Line fitted through all homes
- Line fitted within each parish
With sorting at 100 percent, the line through all simulated homes rises by 11.1 percent for each bioscore point, which is 4.4 times the 2.5 percent within the parishes.
The research behind the two figures is on the Biodiversity page. Nature in the Business Case applies the within-parish figure to the homes near a project.
How it works
The simulation contains 300 homes in five parishes, with prices measured in logarithms, as in the research, so that a difference of 0.01 is read as 1 percent. Each simulated price is the sum of three parts, of which the first is a difference of 2.5 percent for each bioscore point that is the same for each home. The second is a price level that the homes of a parish share, which rises with the average bioscore of the parish in proportion to the slider. The third is a random part, which is kept small so that the pattern remains visible.
The line through all homes is a least-squares fit of the price on the bioscore, which is the straight line with the smallest sum of squared vertical distances to the dots. The lines within the parishes come from the same fit after the parish average of the price and of the bioscore has been subtracted from each home, which is what parish fixed effects do in a regression (Angrist and Pischke 2009). Because that subtraction removes the shared price level of a parish, the slope within the parishes stays at 2.5 percent at each setting of the slider.
The homes are constructed so that the two fitted slopes equal the figures of the research when the slider is at 100. The random part is made unrelated to the bioscore in this sample of homes, after which the price level of the parishes is scaled until the line through all homes rises by 11.1 percent for each bioscore point.
What my current research finds
The two figures come from about 740,000 Danish home sales from 2015 to 2025, each matched to the bioscore of the Biodiversitetskort, the national biodiversity map, in its 2021 edition (Ejrnæs et al. 2021). With no adjustment, one additional bioscore point within 1 kilometre of a home is associated with about 11 percent higher prices. When satellite greenness and the characteristics of each home and its location are held constant across all homes, the figure is about 8.6 percent. When the same comparison is made only among homes of the same type in the same parish, in 2,091 parishes, it is about 2.5 percent.
Holding those characteristics constant accounts for 29 percent of the gap between the unadjusted figure and the within-parish figure, while the comparison within parishes accounts for the remaining 71 percent. I attribute most of that second part to sorting between parishes. The parishes with a high bioscore also differ in other respects, such as access to the coast, commuting distance and the housing stock. A comparison within parishes removes the differences in price level between parishes, although it cannot rule out sorting within a parish, since buyers who value nature may outbid others for the homes nearest to rich habitat. The simulation contains no sorting within a parish, no controls and one type of home.
Sources
- My current research on the price of ecological quality in Danish housing markets, at Aarhus University. Since it is not yet peer-reviewed, the figures may change before it is published. The homes in the chart are simulated in the browser.
- Angrist, J. D. and Pischke, J.-S. (2009). Mostly Harmless Econometrics: An Empiricist’s Companion. Princeton University Press.
- Ejrnæs, R., Bladt, J., Moeslund, J. and Brunbjerg, A. K. (2021). Biodiversitetskortets bioscore. Videnskabelig rapport fra DCE nr. 456. Aarhus Universitet, DCE – Nationalt Center for Miljø og Energi.
Where the tools come from
Several of these tools use methods from How to Measure Anything in Project Management, which I co-authored. Others come from my current research on how the selection of projects affects their results against the estimates and on the value of nearby nature. The talks on the speaking page cover the same material in more depth.