In the book's 37 cost reference classes, the median ratio of actual to estimated cost lies between 1.00 and 1.65
Appendix 2 of the book reports the ratio of actual cost to estimated cost for 37 types of project. Each type forms a reference class, which is a group of completed projects of the same type whose outcomes are used to forecast a new project of that type. The median ratio is 1.13 for roadways and 1.00 for IT projects, which means that the actual cost of the median IT project equalled its estimate. The 95th percentile, the level that one project in twenty exceeds, is 1.95 for roadways and 3.35 for IT projects.
Source: Table A2.1 in Hubbard, Budzier & Leed (2025), How to Measure Anything in Project Management, Wiley.
Does not show: a single overrun rate for all projects. The median differs by type of project, from 1.00 in seven classes to 1.65 for nuclear power. The table covers only estimates made at the final investment decision, when the decision to build a project is taken.
In a calibrated model, selection accounts for roughly 25 to 50 percent of observed cost overruns in most infrastructure categories
When an authority ranks candidate projects by the ratio of their estimated benefits to their estimated costs, known as the benefit-cost ratio, and funds those with the highest ratios, it tends to pick projects whose costs were underestimated. The funded projects then exceed their cost estimates on average even when no single estimate is biased. In my current research, where the result is still preliminary, a model calibrated to the estimating accuracy typical of final investment decisions attributes roughly 25 to 50 percent of observed cost overruns in most infrastructure categories to this selection effect, with a central estimate of about one third.
Source: my current research at Aarhus University, a working paper in progress. An earlier draft is on SSRN (Working Paper No. 6429358) and does not contain these figures.
Does not show: that optimism bias, the tendency of planners to produce estimates that are too optimistic, is absent, since selection accounts for only part of the observed overruns. For dams, the category with the largest average overrun of the eight examined, the central estimate of the share explained by selection is about 12 percent. The shares are calculated on the assumption that projects are selected on their benefit-cost ratios alone. They are lower where other criteria also influence the choice.
One bioscore point of nearby ecological quality is associated with about 2.5 percent higher house prices
The bioscore is the index of ecological quality in the Biodiversitetskort, the national biodiversity map of Denmark, scored from 0 to 19. My current research matches it, averaged within 1 kilometre of each home, to 741,867 Danish home sales from 2015 to 2025. Among homes of the same type in the same parish, one additional bioscore point is associated with about 2.5 percent higher prices, about €7,200 at the median sale price of about €281,500 (95 percent interval about €5,200 to €9,200). Homes of the same type in the same parish typically differ by about 0.58 points, a difference associated with about 1.5 percent higher prices, or about €4,200.
With no adjustment, one bioscore point is associated with about 11 percent higher prices, which is more than four times the within-parish figure. When satellite greenness and the characteristics of each home and its location are held constant across all homes, the figure is about 8.6 percent. Holding those characteristics constant accounts for 29 percent of the fall from 11 to 2.5 percent, while the comparison within parishes accounts for the remaining 71 percent. I attribute most of the gap between 8.6 and 2.5 percent to sorting between parishes, the tendency of buyers who value nature to settle in parishes with high scores.
Source: my current research at Aarhus University, a working paper in progress titled The Price of Biodiversity: Hedonic Evidence from Danish Housing Markets. The research reports amounts in Danish kroner, which are converted here at 7.46 kroner per euro.
Does not show: a causal effect or a price for any particular place. The estimates are associations that measure the part of the value of ecological quality that buyers pay for through the price of a home, which leaves out the value people place on nature they do not live near. The results are preliminary, come from an unpublished paper and may change before release.
In repeated sales of the same house, a one-point rise in the High Nature Value index is associated with about 1.0 percent higher prices
A second analysis in my current research follows about 48,000 detached houses through about 103,000 repeated sales, so that each house is compared with itself at an earlier sale. The High Nature Value index is updated each year. It gives farmland and protected open habitat that depends on grazing or mowing a score from 0 to 13 according to its estimated value for threatened and rare biodiversity. A one-point rise in the index within 250 metres of a house between two sales is associated with about 1.0 percent higher prices, about €2,800 at the median price. Because the bioscore and the High Nature Value index have different scales, the two results can also be stated per standard deviation, the typical difference in an index between homes. Stated in that way, the two analyses give about 2.5 and 2.0 percent higher prices. They agree in direction and each is statistically significant.
Source: my current research at Aarhus University, the same working paper in progress. The research reports amounts in Danish kroner, which are converted here at 7.46 kroner per euro.
Does not show: a causal effect. Part of the measured change in the index reflects registration, meaning new reporting of nature data, and not change on the ground. The result is preliminary and may change before release.
For 80 percent certainty, a rail estimate made at the decision to build needs a cost uplift of 60 percent
An uplift is a percentage added to a cost estimate, derived from how far the actual costs of completed projects of the same type were from their estimates. A report for the UK Department for Transport formed a reference class of 355 completed rail projects from the United Kingdom and other countries. In that class 80 percent of the projects had a cost overrun of 60 percent or less against the estimate at the Full Business Case stage, when the decision to build is taken. Half of the projects had a cost overrun of 19 percent or less. Data from 2,522 new-build rail, road, bridge and tunnel projects show that the risk of overrun is larger for estimates made at earlier stages.
Source: Budzier & Leed (2021), Updating the Evidence Behind the Optimism Bias Uplifts for Transport Appraisals, Oxford Global Projects for the UK Department for Transport.
Does not show: one uplift for all projects. The uplifts differ by type of project and are higher at earlier stages. For the same level of certainty the uplift for rail is 121 percent at the Strategic Outline Business Case stage, the earliest of the three stages that the report covers.
The mean cost overrun across clean-energy projects is 84 percent with nuclear power included and 17 percent without it
A study published in the journal iScience in 2025 assembled a dataset of more than 1,100 clean-energy and industrial decarbonisation projects, of which 482 have data on cost overruns and 401 on schedule overruns. The mean cost overrun is 84 percent and the mean schedule overrun is 51 percent. When nuclear power projects are excluded, the means are 17 percent for cost and 39 percent for schedule. For projects completed since 2000 the mean cost overrun is 36 percent.
Source: Greig, Techau, Leed & Budzier (2025), Maintaining capital discipline in the rush to net-zero energy systems, iScience 28(4), 112241.
Does not show: that each technology performs alike. Solar generation was delivered closer to budget and schedule than the other technologies in the study.
The AI analysis for Hong Kong's early-warning system used cashflow data from 849 completed public works projects
The Hong Kong Development Bureau uses the Project Supervision System (PSS) to monitor capital works projects and to give senior management early warning of cost overrun and delay. The AI analysis described in a report that the Bureau published in 2022 used cashflow data, meaning the spending of each project over time, from 849 completed projects with a total final cost of HKD 460 billion in 2019 prices.
Source: Flyvbjerg, Budzier, Agard & Leed (2022), AI in Action, Hong Kong Development Bureau (PSGO).
Does not show: how many projects the system monitors today or how accurate it is. In the test reported in 2022, the best algorithm assigned the correct warning flag for cost, a red, amber or green status, in 53 to 69 percent of cases, depending on the flag.
80 percent of the Hong Kong models' cost predictions fall within 10 percent of the actual outcome
The models presented in 2024 predict the cost overrun and the schedule overrun of a project from its spending during delivery together with its planned budget, planned duration and type. They also classify whether a project will overrun, with an accuracy of 91 percent for cost and 88 percent for schedule.
Source: Dallachiesa & Leed (2024), Guarding Public Works Projects with an Early Warning System for the Hong Kong Development Bureau, presentation at Machine Learning Week Europe 2024.
Does not show: forecasting accuracy in general. The figures come from cross-validation, in which each model is fitted on a part of Hong Kong's completed projects and tested on the remainder. Balanced accuracy, which gives equal weight to projects that overran and projects that did not, is 84 percent for cost and 77 percent for schedule. For schedule, 80 percent of the predictions fall within 45 percent of the actual outcome.
For 80 percent certainty, the cost estimate for nuclear waste storage needed an uplift of 202 percent
A 2018 study of the planned Swiss deep geological repository for nuclear waste built a reference class of 216 completed projects, of which 22 were nuclear waste storage projects and 194 were nuclear new builds. In that class the median cost overrun was 67 percent, while 80 percent of the projects had a cost overrun of 202 percent or less. A contingency is an allowance for risk that is added to a cost estimate. If the estimates of the 216 projects contained no contingency of their own, a contingency of about 23 percent, the level in the Swiss cost study of 2016, would have been sufficient for 28 percent of them.
Source: Budzier, Flyvbjerg, Garavaglia & Leed (2018), Quantitative Cost and Schedule Risk Analysis of Nuclear Waste Storage, SSRN Working Paper No. 3303410.
Does not show: a forecast for nuclear waste programmes in other countries, since the study concerns the Swiss repository alone. Most of its reference class, 194 of the 216 projects, consists of nuclear new builds.
I compared the budget of the new Aarhus stadium with data on 88 other stadium projects
I made the comparison in 2024 and identified the projects among the 88 that are comparable with the stadium in Aarhus. Jyllands-Posten reported it in November 2024 and TV2 Østjylland in December 2024.
Source: coverage in Jyllands-Posten (November 2024) and TV2 Østjylland (December 2024), both linked from the Speaking page.
Does not show: a cost overrun figure for stadiums in general. Please ask me for the underlying figures before quoting a magnitude.